Consider three mutually exclusive projects (A, B, and C)


Cash Flows A B C

First Cost 1,850.00 $1,850.00 $1,900.00

Uniform annual benefit $90.00 315.00 325.00

Salvage value 135.00 405.00 $360.00

Useful life, in years 6 7 8


When each project reached the end of its useful life, it would be sold for its salvage value and there would be no replacement. Plot the net present worth (NPW) of each project on the same chart with interest rates ranging from 0% to 25%