One worker takes 20 hours to do a job. A second worker can do the same job in 15 hours. When a third worker is added, it takes the three of them 6 hours to do the job. How long would it take the third worker to do the job

Respuesta :

Answer:

20 hrs

Step-by-step explanation:

t = third worker

1 / ( 1/20 + 1/15 + 1/t)  = 6

1 = 6/20 + 6/15 + 6/t

3/10 = 6/t

t = 20 hrs